Scenarios: At the End of a Sprint on a Scrum Project, Which is Better, A or B?

vggg9b-a-or-b---asg-vggggg-lr-squashed



Take a look at the results at the end of a sprint on a Scrum project. There are two scenarios.

a-or-b---asg---v171204-0028for-blog0029-3-2-squashed

As shown above, both have the same user stories with the same story points for each:

  • User story 1: 13 story points
  • User story 2: 8 story points
  • User story 3: 3 story points
  • User story 4: 5 story points
  • User story 5: 1 story point
  • User story 6: 3 story points
  • User story 7: 1 story point

A closer look at both of the scenarios follow.

black_spacer_lr_sq_v3

Scenario A

a-or-b-0028a0029---asg---v171204-lowerres-squashed

Here are some details on A:

  • User story 1: 70 hours of work performed, 5 hours of work remaining
  • User story 2: 51 hours of work performed, no work remaining (and it meets the Definition of Done [DoD])
  • User story 3: 45 hours of work performed, 13 hours of work remaining
  • User story 4: 29 hours of work performed, no work remaining (and it meets the DoD)
  • User story 5: 3 hours of work performed, 2 hours of work remaining
  • User story 6: 30 hours of work performed, 17 hours of work remaining
  • User story 7: 4 hours of work performed, 1 hour of work remaining

A is summarized as:

  • 232 hours of work was performed, and 38 hours of work remains
  • 2 user stories were done, and 5 user stories were not completed

black_spacer_lr_sq_v3

Scenario B

a-or-b-0028b0029---asg---v171204-lowerres-squashed

Here are some details on B:

  • User story 1: 75 hours of work performed, no work remaining (and it meets the DoD)
  • User story 2: 51 hours of work performed, no work remaining (and it meets the DoD)
  • User story 3: 58 hours of work performed, no work remaining (and it meets the DoD)
  • User story 4: 29 hours of work performed, no work remaining (and it meets the DoD)
  • User story 5: 5 hours of work performed, no work remaining (and it meets the DoD)
  • User story 6: 14 hours of work performed, 33 hours of work remaining
  • User story 5: no work performed, and five hours of work remaining

B is summarized as:

  • 232 hours of work was performed, and 38 hours of work remains
  • 5 user stories were done, and 2 user stories were not completed

black_spacer_lr_sq_v3

What Counts

a-or-b-0028conclusion0029---asg---v171204-lowerres-squashed

Scrum requires teams to build an increment of functionality during every sprint. Only work meeting the Definition of Done (DoD) is counted as complete, demonstrated at the sprint review meeting, and is potentially shippable.

There were two scenarios. Both had the same user stories with the same story points for each, and the same amount of work hours performed. Yet the outcomes were dramatically different. In A, 2 user stories were done--and are to be demonstrated at the sprint review meeting, and are potentially shippable. In B, 5 user stories were done--and are to be demonstrated at the sprint review meeting, and are potentially shippable. B is the better scenario.

A possible explanation for the differences between the two situations is that the Scrum team in B may have done a better job of limiting Work in Progress.

black_spacer_lr_sq_v3

About Agile Scrum: Your Quick Start Guide with Step-by-Step Instructions

To learn more about agile/Scrum, check out the award-winning book, Agile Scrum: Your Quick Start Guide with Step-by-Step Instructions. It's offered in digital and print formats.

The ebook (ASIN: B01FZ0JIIY) is available in:


The
paperback (ISBN-13: 9781533370242) is for sale at:


black_spacer_lr_sq_v3

Let's Connect

AgileScrumGuide_-_Follow_Up_on_Twitter_-_v22020407-ASG-BLG-LR-SQ

Connect with
AgileScrumGuide.com on Facebook, Twitter, LinkedIn, Instagram, and Pinterest.

And c
onnect with agile project management practitioner, consultant, award-winning author, and international speaker Scott M. Graffius on Twitter, Facebook, and LinkedIn.

black_spacer_lr_sq_v3



© Copyright 2018 Scott M. Graffius, AgileScrumGuide.com. All rights reserved. This material may not be published, broadcast, rewritten or redistributed without the express written permission of Scott M. Graffius/AgileScrumGuide.com.



Award-Winning Book -Agile Scrum